 | The 1000-Islands Gananoque Holiday Inn Express Hotel & Suites opened in July 2005. For pictures of the interior and amenities Click on the Holiday Inn Express on the left side of your screen.
|
 | Drywall instalation at the Holiday Inn Express in Gananoque February 4, 2005 - Drywall installation is beginning on the first floor as the contractors work their way to the top floor.
|
 | February 4, 2005 - Wiring and plumbing services are being installed throughout the project.
|
 | February 4, 2005 - The pool area is ready for its finishing touches.
|
 | February 4, 2005 - With the building closed up work is underway on the interior. This is the expansive lobby and Breakfast Bar area.
|
 | January 3, 2005 - Roofing will be completed this week while inside the plumbing and wiring is well underway.
|
 | November 22, 2004 - The roof is being framed and the brickwork is proceeding.
|
 | October 24, 2004 - The structure awaits windows and the roof.
|
 | October 6, 2004 - Two views of the work underway - top from the west and bottom, from the east. The second story is being prepared to accept the third floor.
|
 | September 28, 2004 - Construction continued on the second floor.
|
 | September 27, 2004 - The second floor is being placed on the structure.
|
 | September 11, 2004 - Interior walls are being erected on the first floor in preparation for the second floor to arrive the following week.
|
 | September 7, 2004 - Basement construction and pool construction are in place which allowed the first floor to be placed on the foundation.
|
 | August 13, 2004 - The steel frame begins to take shape awaiting construction of the indoor pool.
|
 | July 18, 2004 - Work on the inside basement walls and other work in the basement is proceeding.
|
 | June 28, 2004 - Work is underway to prepare forming for the second half of the foundation.
|
 | June 25, 2004 - Concrete is pumped into the forms.
|
 | June 23, 2004 - Forms for the first half of the concrete foundation are in place.
|
 | June 19, 2004 - The footings are in place following an extensive excavation.
|
|
|
|